New Seating Terrace Completed

Updated: Nov 24, 2019

Many Thanks to John Jonas and his merry band of volunteers for all the hard work put in over the last few weeks. After several sessions in Sept/Oct in clearing the bushes and digging out the soil a concentrated effort was made during week of 28th October to level the ground and lay the hardcore finishing that week on Friday 1st November by laying the concrete. The work started at 9am and in between heavy showers managed to finish by 4pm. Special thanks to David Holmes for his mentoring and Terry Hammond, Ian Robertson, Graham Roberts and Alan Fogden supplying the mixed concrete to John and David. An idea was put forward then John immediately started the next phase by completing an ornamental brick seating wall and special planting area. Well Done.

A wonderful job where we can sit and appreciate the view of the Green.



44 views0 comments
  • White Instagram Icon